Case study · Construction

Know a job's margin before it is finished

Contractors often discover a job lost money months after it ended, because committed costs, subcontractor claims and valuations sat in different places. This is how we brought them together in Business Central so every job shows its real position every month.

Project overview

Business Central job costing extended for construction.

Industry
Construction
Client
Confidential
Solution
Job costing and valuations
Platform
Business Central
Timeline
14–22 weeks
Team
4 people
Commercial model
Fixed price and variations
Special rules
Retentions, CIS / withholding tax
Deployment
Business Central online

Expected business outcomes

What the client set out to achieve

The value is in seeing committed cost early. These ranges depend on how consistently site teams raise purchase orders.

  • Monthly Cost-to-complete per job

    Actual, committed and forecast cost per job every month, instead of at final account.

    Depends on purchase orders being raised before orders are placed

  • 30–50% Less time on valuations

    Valuations and applications for payment are prepared from job data rather than rebuilt in spreadsheets.

    Target range after the first three valuation cycles

  • Near zero Unapproved supplier invoices

    Invoices match to purchase orders and goods receipts, so nothing is paid that wasn't ordered.

    Where three-way matching is enforced

Business challenges

How job costing worked before

Site and office each have part of the picture, and nobody has all of it.

Buying

Site managers order materials by phone; the office finds out when the invoice arrives.

Subcontractors

Applications and retentions are tracked in a spreadsheet per job.

Valuations

Quantity surveyors prepare valuations in Excel from their own records.

Accounts

The accounting package records costs by supplier, not by job and cost code.

Management

Margin per job is only known at final account, too late to recover a loss.

Proposed solution

What the Business Central build covers

Business Central Jobs, extended where construction works differently from standard project accounting.

  • Jobs and cost codes

    Every job with a cost breakdown by trade or cost code and a budget from the tender.

  • Purchase commitments

    Purchase orders raised against job and cost code, so committed cost shows before the invoice.

  • Subcontractor ledger

    Subcontract orders, applications, certifications and retentions per subcontractor and job.

  • Valuations and applications

    Applications for payment prepared from job progress, with retention and contra charges.

  • Cost-to-complete

    Actual, committed and forecast to complete per job and cost code, reviewed monthly.

  • Site requisitions

    A simple mobile form for site teams to request materials against the right job.

Project requirements

What the client asked us for

The request was 'one system instead of three spreadsheets', but the real need is committed cost: knowing what has been ordered before the invoice arrives.

That means the process change matters as much as the software. Site teams have to raise requisitions, so we make that easier than phoning a supplier.

What the project had to deliver

  • 01Committed cost visible per job
  • 02Subcontractor retentions tracked automatically
  • 03Valuations from the same data as the accounts
  • 04Monthly cost-to-complete reviews

Key challenges & considerations

What made it harder, and what we did

  1. Site teams used to ordering by phone

    What we did

    Site requisitions were put on a phone and kept to a few taps, so raising an order was quicker than phoning it in.

  2. Variations agreed on site and recorded late

    What we did

    Variations were recorded on site as they were agreed, then priced and approved in the same flow.

  3. Retentions held for years on old jobs

    What we did

    Retentions on old jobs were loaded before go-live, each with its release date and a reminder.

  4. Industry tax schemes for subcontractors

    What we did

    Subcontractor tax deductions were configured and tested against real payment runs before the first live one.

What we watched for

  • Make site requisitions quicker than a phone call
  • Load retentions for old jobs before go-live
  • Agree cost codes with commercial, not just finance
  • Review forecasts monthly or they go stale

Development process

Built around the monthly job review

The project is designed backwards from the cost-to-complete review the directors hold every month.

  1. Stage 1

    Cost structure

    Cost codes, budget templates and job setup agreed with commercial and finance.

  2. Stage 2

    Buying and requisitions

    Purchase order approvals and the site requisition form, piloted on two live jobs.

  3. Stage 3

    Subcontractors and retentions

    Subcontract orders, applications and retention release rules configured and tested on historic cases.

  4. Stage 4

    Valuations and go-live

    Valuations moved onto job data, with opening balances for every live job.

  5. Stage 5

    Monthly reviews

    The first cost-to-complete reviews run with the directors, then refined.

Technology stack

Business Central Jobs, extended for construction

Standard jobs and purchasing, with an AL extension for subcontractor and retention rules.

ERP

  • Business Central Jobs
  • Purchasing and approvals
  • AL extensions

Site

  • Power Apps requisition form
  • Mobile approvals

Reporting

  • Cost-to-complete reports
  • Power BI

Integration

  • Business Central APIs
  • Document capture

Quality assurance & deployment

Proved on the client's own data before go-live

An ERP is trusted when the numbers agree. Configuration and extensions were tested in a sandbox on the client's own data, and finance signed off the figures before cut-over.

  • Sandbox testing of every process on the client's own data
  • User acceptance testing with key users, by scenario
  • Migration rehearsals, reconciled to the old system
  • Automated tests for extensions, run before each release
  • Permission sets checked role by role

Deployment

  • 01Valuations and go-liveValuations moved onto job data, with opening balances for every live job.
  • 02Monthly reviewsThe first cost-to-complete reviews run with the directors, then refined.
  • 03Cut-over planA rehearsed cut-over with a checklist, opening balances signed off by finance, and a rollback point.
  • 04Hypercare and warrantyConsultants on hand through the first month-end, and six months of free bug fixing.

Final deliverables

Every job's position, every month

Directors review each job's actual, committed and forecast cost monthly, and problems are discussed while there is still time to recover them.

Quantity surveyors prepare valuations from the same data finance uses, so the two stop disagreeing about what a job has cost.

  • Committed cost before invoices arrive
  • Subcontractor retentions tracked to release
  • Valuations from job data
  • Monthly cost-to-complete per job

Handed over to the client

  • 01Configured Business CentralProduction and sandbox environments
  • 02ExtensionsSource code and documentation
  • 03Migrated dataReconciled and signed off
  • 04Key-user trainingWith process guides
  • 05Six-month warrantyFree bug fixing after delivery

Success metrics

How success is measured

MeasureOutcomeHow it is measured
Cost-to-complete per job Monthly Depends on purchase orders being raised before orders are placed
Less time on valuations 30–50% Target range after the first three valuation cycles
Unapproved supplier invoices Near zero Where three-way matching is enforced

Verified reviews

What clients say about our Dynamics work

Verified reviews from our clients on the same kind of work, published on Clutch.

5.0 27 verified reviews

Free discovery call

Have an idea? Let's turn it into AI-powered software.

Book a free discovery call with our experts. Share your idea and we will help you shape the scope, timeline and budget, under NDA.

  • Free consultation
  • NDA before we talk
  • Transparent estimate